Blog · Finance metrics and formulas · Oil and gas

Oil and gas services cost analysis

Compare oilfield job costs by crew, service line and customer using operating and expense exports. Calculate crew, equipment, mobilization and subcontractor costs, allocate shared overhead and reconcile the result to the ledger.

The short answerOil and gas services cost analysis compares the crew, equipment, mobilization, subcontractor and allocated overhead costs of oilfield jobs. Match time records, equipment logs and supplier charges to a common job ID, reconcile the costs to the ledger, and compare actual spending with a consistent budget. Separate changes in activity from changes in rates before assigning corrective action.

Oil and gas services cost analysis starts by putting crew, equipment, mobilization and subcontractor charges against the job that used them. Compare the resulting cost with the approved budget, then separate extra activity, changed rates and shared-cost allocations before deciding what to fix.

For an oilfield service company, the practical question is whether a crew or service line is consuming more resources than planned. This review concerns the service company's operating costs; broader results belong in oilfield services financial analysis.

Assemble the job-cost export

Start with completed jobs for a defined reporting period. Keep job ID, customer, service line, crew, location and completion date as grouping fields. Retain source transaction IDs so every summarized amount can be traced to a time entry, equipment log or supplier charge.

Bring these records together through the job ID:

  • Approved crew hours and loaded labor rates, including the agreed treatment of overtime and travel time.
  • Equipment hours and the internal or rental rate used in the budget.
  • Mobilization charges, including transport and separately billed movement costs.
  • Supplier invoices and accruals for subcontractors and other job-specific spending.
  • The shared support-cost pool and its allocation driver.

Do not add payroll detail to a ledger labor total that already includes it. Use the detail to distribute and explain that total. The same rule applies when equipment rental invoices already sit in the job ledger.

IRS Publication 538 describes the basic accrual distinction between incurring an expense and paying it. Apply the company's accounting policy when capturing completed-job costs, including supplier charges incurred but not yet invoiced. A payment-date extract alone can leave a finished job looking artificially cheap.

Calculate direct costs from the operating rows

The example is a fictional US oilfield services company reviewing three completed jobs in the same service class. These are management costs in USD, not market benchmarks. The crew's loaded rate and equipment rate are established inputs; all hours have been approved.

Use A:H for the following input columns, with headers in row 1 and jobs in rows 2-4.

Job Crew hours Crew rate (USD/hour) Equipment hours Equipment rate (USD/hour) Mobilization (USD) Subcontractors (USD) Budget (USD)
A 500 42 40 250 5,000 4,000 42,000
B 600 45 50 250 8,000 6,000 48,000
C 400 42 30 250 4,000 3,000 33,000
Total 1,500 120 17,000 13,000 123,000

Enter these formulas in I2:K2 and fill them through row 4:

I2 = B2*C2
J2 = D2*E2
K2 = SUM(F2:G2,I2:J2)

Column I is crew cost, J equipment cost and K direct job cost. Job B therefore carries $27,000 of crew labor, $12,500 of equipment cost, $8,000 of mobilization and $6,000 of subcontractors: $53,500 before shared support.

An equipment rate may include depreciation and maintenance for owned assets. IRS Publication 946 explains depreciation as recovering qualifying property cost over its use; tax deductions are a separate schedule from this management allocation. Do not add an equipment purchase payment to a job that already bears a usage charge for the same ownership cost.

Allocate support costs and compare with budget

For this example, shared field supervision and dispatch total $27,000. Enter that pool in B7. The company allocates it by crew hours because those services primarily support crews. This is an explicit example policy, not a rule for every cost pool.

Add the following columns:

L2 = $B$7*B2/SUM($B$2:$B$4)
M2 = K2+L2
N2 = M2-H2
O2 = IF(H2<>0,N2/H2,"Review")
P2 = IF(B2>0,M2/B2,"Review")

L is allocated support, M full cost, N dollar variance, O variance percentage and P full cost per crew hour. Fill through row 4. A positive variance is unfavorable because actual cost exceeds budget.

Job Crew cost (USD) Equipment cost (USD) Direct cost (USD) Support (USD) Full cost (USD) Variance (USD) Variance
A 21,000 10,000 40,000 9,000 49,000 7,000 16.7%
B 27,000 12,500 53,500 10,800 64,300 16,300 34.0%
C 16,800 7,500 31,300 7,200 38,500 5,500 16.7%
Total 64,800 30,000 124,800 27,000 151,800 28,800 23.4%

Support is $27,000 divided by 1,500 crew hours, or $18 per crew hour. Job B receives 600 times $18 = $10,800. Its $64,300 full cost exceeds its $48,000 budget by $16,300. Percentages use each row's budget and are rounded to one decimal place.

The total variance is $151,800 - $123,000 = $28,800. Divide those totals for the overall 23.4%; do not average the job percentages. The allocation check is:

=SUM(L2:L4)-B7

It must return zero. Also prove that $64,800 labor + $30,000 equipment + $17,000 mobilization + $13,000 subcontractors = $124,800 direct cost, then add $27,000 support to reach $151,800. Reconcile each category to the ledger and document any excluded non-job costs.

Explain the largest movement before assigning action

Job B has the largest dollar overrun. Start with its labor estimate rather than assuming all of the excess reflects wage inflation.

Job B labor comparison Hours Rate (USD/hour) Cost (USD)
Approved labor estimate 500 42 21,000
Actual labor 600 45 27,000
Increase 100 3 6,000

The hours effect is (600 - 500) times $42 = $4,200. The rate effect is 600 times ($45 - $42) = $1,800. Together they explain the $6,000 increase without a residual. Compare travel, standby, rework and scope changes to the approved job record before choosing an action.

Full cost per crew hour is $98.00 for A, $107.17 for B and $96.25 for C, rounded to cents. Those figures flag B for investigation; they do not prove inefficient delivery when scope or operating conditions differ. Review oil and gas services revenue analysis separately when the question is whether extra work was billed.

Where it goes wrong

  • Missing late charges. An unposted subcontractor invoice can make a completed job look favorable. Track accruals and subsequent reversals.
  • Allocating overhead twice. Exclude direct charges from the support pool before spreading that pool across jobs.
  • Changing the driver between budget and actual. A crew-hour actual against a revenue-based budget allocation mixes operating change with measurement change.
  • Comparing different job scope. More hours may represent more delivered work, standby or rework. Keep those explanations separate.
  • Treating blanks as zero. A missing equipment rate is an exception, not evidence that equipment had no cost.

Operations should confirm hours and scope, procurement should confirm supplier charges, and finance should own the ledger reconciliation and allocation policy. A services cost analysis uses similar labor discipline, while an oil and gas services dashboard can organize the measures for recurring review.

Compare your own oilfield job costs in Covirage

Upload a job-cost file with the crew, equipment, supplier and budget fields retained; Covirage maps the columns, and its tools compute and check the comparisons. The external AI model explains the result with every figure traced to its rows. Create a free Covirage account, which takes about a minute, and bring a sample of your own data.

See cost variance analysis for the supporting cost-control approach.

Questions people ask

Which costs should an oilfield job analysis include?

Include attributable crew labor, equipment use, mobilization, consumables and subcontractor charges. Add a clearly labeled share of support costs for a full-cost view. Keep capital purchases and financing separate from operating charges, and retain the cost policy used for both budgets and actuals.

How should shared oilfield operating costs be allocated?

Choose a driver related to the support being consumed, such as crew hours for shared field supervision or equipment hours for maintenance support. State the cost pool and driver explicitly, allocate the entire pool once, and retain an unallocated category for exceptions.

Is cost per crew hour a productivity measure?

It is a cost-intensity measure, not a complete productivity measure. A job can have a lower hourly cost while taking more hours to deliver the same work. Compare scope, service type, standby time and completion output before drawing an operational conclusion.

How do you compare jobs completed in different months?

Use the same cost definitions and distinguish completed jobs from work still in progress. Include accrued supplier charges where appropriate, retain the month of the underlying activity, and compare similar service scope rather than treating every job as interchangeable.