Blog · Finance metrics and formulas · Construction
Reconcile an owner's construction-in-progress balance to cash capital spending. Separate additions, transfers to completed assets and capital payables, with a worked project reconciliation and cash-flow classification checks.
Construction in progress on a cash flow statement appears through cash paid to build the company's own long-term assets, generally as an investing outflow. The construction-in-progress balance itself stays on the balance sheet. Its movement can include unpaid invoices and transfers to completed assets, so subtracting opening CIP from closing CIP will not give cash capital expenditures.
This reconciliation concerns a company building a warehouse, office or production facility for its own use. Construction in progress, or CIP, accumulates the capitalized costs of that unfinished property, plant and equipment. The accounting question is how those asset movements connect to cash payments.
A contractor building for a customer has a different business transaction. Its work-in-progress schedules support contract accounting, billings and operating results; the customer may own the eventual facility. Likewise, property developed for ordinary resale is inventory rather than an owner-used fixed asset. Do not apply an owner-asset cash capex formula to either situation without first classifying the underlying activity.
The SEC's financial statement guide distinguishes purchases of long-term assets in investing activities from business operations and borrowing. That separation is the starting point; the asset's purpose and the payment's nature determine the classification.
For contractor receipt and subcontractor timing, use cash flow for a construction project. Here the owner is paying to acquire its own facility.
Bring the opening and closing CIP balances, project-level additions, transfer entries and payment register. Add capital accounts payable and accrued construction costs at both dates. Include project IDs, invoice IDs, posting dates, payment dates, vendor amounts and the destination fixed-asset account.
Separate operating payables from capital payables even when both use the same ledger control account. A construction invoice can be capitalized before payment, and an opening payable can be paid without creating a current-period addition. The accrual versus cash accounting guide explains why recognition and payment need separate dates.
Before applying the simplified bridge below, isolate asset acquisitions, leases, foreign-exchange movements, impairments, write-offs and transfers from other asset categories. Capital advances also need their own opening-to-closing bridge. A cash deposit can precede the CIP addition, so an additions-and-payables formula alone will miss it.
Consider an illustrative US company expanding facilities during one reporting year. The following amounts are gross asset costs in USD. There are no capital advances, interest, leases, acquisitions, impairments or currency movements in this example.
Closing CIP = Opening CIP + Capital additions - Transfers to completed assets
| Project | Opening CIP (USD) | Capital additions (USD) | Transfers out (USD) | Closing CIP (USD) |
|---|---|---|---|---|
| Warehouse expansion | 500,000 | 700,000 | 600,000 | 600,000 |
| Production building | 300,000 | 500,000 | 300,000 | 500,000 |
| Total | 800,000 | 1,200,000 | 900,000 | 1,100,000 |
For the warehouse, $500,000 + $700,000 - $600,000 = $600,000. For the production building, $300,000 + $500,000 - $300,000 = $500,000. The total check is $800,000 + $1,200,000 - $900,000 = $1,100,000.
Transfers explain why the $300,000 increase in CIP is much smaller than additions. Those transfers increase completed property by the same $900,000. They do not change total gross property or create a payment.
As a second asset check, suppose completed gross property starts at $3,200,000 and has no movements except these transfers. It ends at $4,100,000. Combined gross property therefore rises from $4,000,000 to $5,200,000, exactly the $1,200,000 of capital additions. All values are whole dollars; no rounding is required.
Assume ordinary vendor payment terms and that all opening capital payables are settled during the year. Closing capital payables consist entirely of unpaid current-year additions. There is no seller financing in the example.
Cash paid for construction = Capital additions + Opening capital payables - Closing capital payables
| Project | Capital additions (USD) | Opening capital payables (USD) | Closing capital payables (USD) | Cash paid (USD) |
|---|---|---|---|---|
| Warehouse expansion | 700,000 | 100,000 | 150,000 | 650,000 |
| Production building | 500,000 | 50,000 | 100,000 | 450,000 |
| Total | 1,200,000 | 150,000 | 250,000 | 1,100,000 |
The warehouse pays $700,000 + $100,000 - $150,000 = $650,000. The production building pays $500,000 + $50,000 - $100,000 = $450,000. Combined construction payments are $1,100,000, reported as an outflow rather than a positive receipt.
The same amount follows from the CIP movement: $300,000 + $900,000 + $150,000 - $250,000 = $1,100,000. The difference between the CIP increase and cash paid is $800,000, explained by transfers out of $900,000 less the $100,000 increase in capital payables.
Tie the two project payment totals to bank-supported disbursement records. Investigate unmatched payments, partial settlements and invoices assigned to the wrong project before accepting the bridge.
Under these assumptions, the company's investing section includes a $1,100,000 construction payment outflow. The remaining $250,000 of unpaid current-year additions is noncash investing activity for disclosure; it is not another current cash outflow. Exclude capital-payable movements from operating working-capital adjustments under the indirect method.
KPMG's US GAAP cash flow handbook, section 8.2.30, illustrates construction payables and cash spending; section 8.5.20 also explains that interest paid and capitalized into PP&E is an investing outflow under ASC 230. Interest is excluded from this worked example. Extended seller financing requires separate assessment rather than treating every later settlement as ordinary investing cash capex.
The controller owns classification and disclosure; project accounting supplies additions and completion transfers, while accounts payable supplies settlement evidence. Use the cash flow statement example to place the completed bridge within the full statement. For planning future payments, use a cash flow forecast.
Bring your CIP rollforward, capital-payables schedule and payment file to Covirage. Covirage maps the columns, and its tools compute and check the asset and cash reconciliations; the external AI model explains the results with every figure traced to its rows. Create a free Covirage account and bring a sample of your own data.
See project cost control for related comparisons of project spending and budgets.
The asset balance itself is neither a cash inflow nor an outflow. Cash payments to build an asset for the company's own use generally belong in investing activities. A contractor's customer jobs and a developer's inventory require a different classification analysis.
No. The transfer moves accumulated cost from the unfinished asset account to the completed asset account. It does not create a new payment. Keep the transfer in the fixed-asset reconciliation and trace actual cash separately to the disbursement records.
Current-period capital additions can include invoices that remain unpaid. Exclude those amounts from current cash spending and include payments of earlier capital payables when settled, subject to their terms and classification. Keep capital payables separate from operating working-capital movements.