Sign in

Project and programme cost control

Know where a large programme stands against its budget, this week.

On a programme of any size, the budget is one file, the purchase orders another, the invoices a third and the forecast a spreadsheet per workstream. Covirage joins them: budget, committed, actual and forecast to complete by workstream, work package and vendor, with contingency, change requests and the burn curve, reconciled to the ledger.

Upload sample data to try itSee a demoProgramme to workstream to work package to vendor, asserted on every upload.
Programme · forecast at completion against budget, by workstreamreconciled ✓
Data migration
+£4.1m
Core platform
+£2.4m
Testing
+£0.8m
Change and training
−£0.3m
Programme office
on budget
TotalForecast £107.0m against £100.0m
4 numbersbudget, committed, actual, forecast to complete
By vendorspend and commitments against each statement of work
Weeklyoverrun watch list by workstream

The overrun, by workstream and vendor, before the steering committee asks

Most overruns are visible months early in the commitments: purchase orders raised above the work package budget, vendors billing faster than milestones, contingency drawn without a change request. Each is in a file the programme already has.

Four numbers per work package

Budget, committed, actual and forecast to complete, rolled up through the programme, with variance at completion.

Burn and contingency

Spend against the planned curve, contingency drawn against remaining risk, and the change requests that moved the baseline.

Vendors and rates

Spend and commitments per vendor against each statement of work, with day rates against the rate card.

How it works

Three steps, in this order.

Send the files

The programme budget, purchase orders, invoices or ledger actuals, and the forecast by workstream.

Confirm the structure

Every cost maps to one work package, and the programme total agrees with the ledger.

Review weekly

The watch list of work packages forecast over budget, ranked by value, with the vendor behind each.

“A hundred million budget is lost one purchase order at a time.”Why commitments are on the first screen

Questions teams ask

Short answers. The Help centre has the long ones.

Does it replace the project management tool?

No. It reads the financial files around it: budget, commitments, actuals and forecast. Schedule and delivery stay where they are.

What about capital and operating cost?

Both are carried, with the split shown, because the programme reports one total and finance reports two.

How are change requests handled?

Each approved change moves the baseline with a date, so variance is shown against the original and the current budget.