Sign in

Project and program cost control

Know where a large program stands against its budget, this week.

On a program of any size, the budget is one file, the purchase orders another, the invoices a third and the forecast a spreadsheet per workstream. Covirage joins them: budget, committed, actual and forecast to complete by workstream, work package and vendor, with contingency, change requests and the burn curve, reconciled to the ledger.

Upload sample data to try itSee a demoProgram to workstream to work package to vendor, asserted on every upload.
Program · forecast at completion against budget, by workstreamreconciled ✓
Data migration
+$4.1m
Core platform
+$2.4m
Testing
+$0.8m
Change and training
−$0.3m
Program office
on budget
TotalForecast $107.0m against $100.0m
4 numbersbudget, committed, actual, forecast to complete
By vendorspend and commitments against each statement of work
Weeklyoverrun watch list by workstream

The overrun, by workstream and vendor, before the steering committee asks

Most overruns are visible months early in the commitments: purchase orders raised above the work package budget, vendors billing faster than milestones, contingency drawn without a change request. Each is in a file the program already has.

Four numbers per work package

Budget, committed, actual and forecast to complete, rolled up through the program, with variance at completion.

Burn and contingency

Spend against the planned curve, contingency drawn against remaining risk, and the change requests that moved the baseline.

Vendors and rates

Spend and commitments per vendor against each statement of work, with day rates against the rate card.

How it works

Three steps, in this order.

Send the files

The program budget, purchase orders, invoices or ledger actuals, and the forecast by workstream.

Confirm the structure

Every cost maps to one work package, and the program total agrees with the ledger.

Review weekly

The watch list of work packages forecast over budget, ranked by value, with the vendor behind each.

“A hundred million budget is lost one purchase order at a time.”Why commitments are on the first screen

Questions teams ask

Short answers. The Help center has the long ones.

Does it replace the project management tool?

No. It reads the financial files around it: budget, commitments, actuals and forecast. Schedule and delivery stay where they are.

What about capital and operating cost?

Both are carried, with the split shown, because the program reports one total and finance reports two.

How are change requests handled?

Each approved change moves the baseline with a date, so variance is shown against the original and the current budget.

Read more

Written for this job: the measures, the data you already hold, and the arithmetic.

Board and management reporting · Manufacturing

NPD dashboard: new product cost and launch progress

Build a new product development dashboard from cost exports and milestone registers. Compare spending, forecast completion cost, and launch readiness with a worked manufacturing example and spreadsheet formulas.

Oct 25, 20265 min read
Board and management reporting

Power BI project management dashboard: costs and progress

Compare approved project budgets, actual costs, and evidenced progress at the same reporting date. A worked portfolio example shows why budget remaining alone cannot establish project health.

Oct 25, 20266 min read
Board and management reporting

Project management report: progress, cost, and exceptions

Build a project management report that connects the approved baseline with incurred costs, open commitments and forecast completion. A worked warehouse installation shows the report tables, spreadsheet formulas and reconciliation checks.

Oct 25, 20265 min read
Territory, capacity and quota planning · Finance and FP&A teams

Cost and schedule control: connect the two reviews

Cost and schedule control compares spending, accepted progress and forecast dates for the same work packages. Follow a shared-cutoff review with export layouts, spreadsheet formulas, a worked example and checks that separate delayed work from real savings.

Oct 24, 20265 min read
Finance metrics and formulas · Finance and FP&A teams

Cost variance: earned value formula and project example

Cost variance compares the budgeted value of completed project work with its actual cost. Calculate it by work package, reconcile the total, and distinguish its sign from an accounting budget variance.

Oct 24, 20265 min read
Board and management reporting

Event management dashboard: bookings, capacity and costs

An event management dashboard compares registrations, attendance, available places, and event costs against plan. Work through a US event portfolio, a change in attendance, and the checks that separate bookings from people and budget from cash.

Oct 24, 20266 min read