Compare subcontractor bids on the same quantities, scope and allowances. Work through a bid-leveling table, spreadsheet formulas and the checks before an award decision.
Construction bid analysis compares proposals after putting scope, quantities, exclusions and allowances on the same basis. Keep the submitted prices intact, then show every adjustment that turns them into comparable amounts. A low comparison total supports a review; it does not establish technical compliance or contractor suitability.
Bring the subcontractors' schedules, scope sheets, clarifications and the estimator's quantity schedule. Record the bid version and date so a revised quote cannot silently replace the one the team reviewed. Use one scope code for the same work across bidders, even when their descriptions differ.
The comparison needs bidder, scope code, unit, submitted quantity, common quantity, quoted unit rate, submitted amount, exclusions and allowance basis. Keep tax, freight, bonding and mobilization visible wherever they are relevant. Either include each consistently or explain its treatment outside the comparison.
The principle has a useful US procurement reference: FAR proposal analysis guidance describes comparing proposed prices and considering differences in quantities, terms and conditions when using comparison prices. It is federal procurement guidance, rather than a private contractor's award policy, but the comparison problem is familiar.
Actual spending belongs in construction budget analysis. This worksheet answers the earlier question: what would the same supplied scope cost under each proposal?
An Ohio general contractor compares two proposals for a warehouse package. The common quantities are 1,000 cubic yards of excavation, 200 cubic yards of concrete and 100 anchors. Testing is required, and the estimator sets a common dewatering allowance of $2,500.
Bidder A priced only 900 cubic yards of excavation, excluded testing and included a $1,000 dewatering allowance. Its confirmed excavation rate applies to the additional quantity. Bidder B priced the full quantities, included testing at $3,000 and carried the common allowance.
| Scope | A submitted amount (USD) | B submitted amount (USD) | Common comparison basis |
|---|---|---|---|
| Excavation | 16,200 | 17,500 | 1,000 cubic yards; rates 18.00 and 17.50 |
| Concrete | 40,000 | 41,000 | 200 cubic yards; rates 200.00 and 205.00 |
| Anchors | 4,000 | 4,500 | 100 each; rates 40.00 and 45.00 |
| Testing | 0 | 3,000 | Common scope allowance 3,000 |
| Dewatering allowance | 1,000 | 2,500 | Common allowance 2,500 |
| Submitted total | 61,200 | 68,500 | Before adjustments |
The zero for A's testing means explicitly excluded, not free. The comparison allowance is an estimator-supplied assumption, not a revised subcontractor quote.
Leveled amount = Submitted amount + Quantity adjustment + Scope adjustment + Allowance adjustment
| Comparison step | Bidder A (USD) | Bidder B (USD) |
|---|---|---|
| Submitted total | 61,200 | 68,500 |
| Excavation quantity adjustment | 1,800 | 0 |
| Add excluded testing | 3,000 | 0 |
| Normalize dewatering allowance | 1,500 | 0 |
| Leveled amount | 67,500 | 68,500 |
A's quantity adjustment is (1,000 minus 900) × $18 = $1,800. Its allowance adjustment is $2,500 minus $1,000 = $1,500. The original $7,300 difference becomes $1,000 after $6,300 of adjustments. A is 1.5% below B on the common basis, calculated as $1,000 / $68,500 and rounded to one decimal place.
Use unit cost analysis for construction to examine rate differences further without mixing that question into scope completeness.
Use these columns on a detail sheet: A bidder, B scope, C unit, D submitted quantity, E common quantity, F confirmed unit rate, G submitted amount, H quantity adjustment, I scope adjustment, J allowance adjustment and K leveled amount.
For a measured item, enter this in H2:
=(E2-D2)*F2
Apply it only where the bidder confirmed that rate for the changed quantity. Enter zero quantity adjustments for lump sums; keep their scope corrections in I and J. In K2, use:
=SUM(G2:J2)
Place the bidder name in M2 and summarize the leveled detail with:
=SUMIFS($K$2:$K$11,$A$2:$A$11,M2)
The SUMIFS documentation explains summing rows that meet specified criteria. Add another criterion for package or bid revision when the workbook contains more than this comparison.
Do not force a lump sum into a made-up unit rate. If a scope item has no usable rate or clarification, record the unresolved amount and keep it visible to the reviewer.
First, tie each submitted total to its signed proposal. Then check that the detail adjustments sum to the comparison bridge: $61,200 + $1,800 + $3,000 + $1,500 = $67,500 for A. B's bridge remains $68,500 because its submitted quantities and allowances already match the common basis.
Review every common scope code for both bidders. An item absent from a schedule needs an explicit inclusion, exclusion or unresolved status. Keep alternate designs outside the base comparison until the technical reviewer approves an equivalent scope.
The estimator owns quantities and comparison allowances. Procurement owns bid versions and commercial clarifications. The project team reviews technical compliance, delivery commitments and capacity before anyone treats the comparison as award support. Carry the accepted package into construction project profitability analysis once it becomes part of the project's expected cost.
Bring the bid schedules and your supplied common-scope adjustments in an uploaded spreadsheet. Covirage maps the columns, and its tools compute and check the comparison totals; the external AI model explains the differences with every figure traced to its rows. Create a free Covirage account, which takes about a minute, and bring a sample of your own export after setting up your business.
See Covirage for construction businesses for the supporting industry context.
Bid leveling adjusts proposals to a common comparison basis. An estimator records quantity differences, missing scope and unequal allowances separately from the submitted prices, keeping the original proposals intact so reviewers can see exactly why the comparison changed.
The lowest amount is one input to an award decision. Reviewers must also assess scope compliance, qualifications, schedule commitments, capacity and contract terms. An unresolved exclusion can make a seemingly low price unsuitable for a like-for-like comparison.
Record the excluded scope and obtain a documented comparison allowance or clarification. Show that adjustment separately from the bidder's price. If the exposure cannot reasonably be priced, mark the comparison unresolved instead of treating the missing work as zero.