The spread of actual lead time, receipt date minus order date, per supplier per site per item: interquartile range or standard deviation. It drives safety stock more than the mean does, and it is invisible on an on-time scorecard.
The same supplier can be steady to one plant and erratic to another. Supplier-level averages the erratic one away.
The ERP's planned lead time was set at item creation. The receipts say what it is now.
Actual lead time is receipt date minus order date. For each supplier, site and item, report the interquartile range and the 90th percentile alongside the median.
Two suppliers both have a median of 20 days. One ranges from 18 to 22 and the other from 10 to 35. The second needs roughly three times the safety stock.
Only the average on the scorecard. Planners carry the cost of the spread and nobody negotiates it.