The six big losses in total productive maintenance

The six big losses separate downtime, slow production and rejected output. Use recorded production exports to compare losses by line and reconcile them to planned production time.

The short answerThe six big losses in total productive maintenance are equipment failure, setup and adjustments, minor stops, reduced speed, process defects and startup rejects. They group production losses into availability, performance and quality. Compare them using recorded stop time, output counts and an ideal cycle time, then reconcile the losses to planned production time.

The six big losses in total productive maintenance explain why scheduled production does not become good output at the ideal production rate. They separate equipment failure, setup and adjustments, minor stops, reduced speed, process defects and startup rejects. Use them to choose a specific improvement on a specific line, with recorded minutes and units behind the choice.

What each loss means

The categories connect maintenance work to production results. OEE.com's six-loss definitions group the first pair under availability, the next pair under performance and the last pair under quality.

Loss What belongs in it First owner to investigate
Equipment failure Significant stops caused by breakdowns or other agreed unplanned reasons Maintenance lead with production
Setup and adjustments Changeovers and adjustments during scheduled production Production lead with setup team
Idling and minor stops Brief interruptions recorded below the significant-stop threshold Line supervisor
Reduced speed Running below the agreed ideal production rate Process engineer with operators
Process defects First-pass rejects during stable production Quality lead
Startup rejects, also called reduced yield First-pass rejects before stable production Setup team with quality

Assign an event to one category. Agree a stop-duration boundary locally, and apply it consistently. A jam recorded as significant downtime cannot also be included in minor-stop minutes.

Keep this analysis narrower than a general manufacturing KPI report. Its purpose is to account for lost productive time, rather than score every part of the plant.

Start with the recorded production export

Use a US packaging manufacturer's shift records. Both lines make the same item, with an ideal cycle time of 0.5 minute per unit. Planned production time already excludes periods when the lines were not scheduled to run.

The export should identify the date, shift, line, item, planned minutes, significant-stop reasons, minor-stop minutes, total units and first-pass reject reasons. Keep the cycle-time reference with the report so a later revision does not silently change history.

Recorded input Line A Line B
Planned production time, minutes 420 420
Equipment failure, minutes 40 15
Setup and adjustments, minutes 20 30
Minor stops, minutes 25 20
Ideal cycle time, minutes per unit 0.5 0.5
Total units produced 600 650
Startup rejects, units 20 10
Process defects, units 10 20

These are illustrative records, not an industry benchmark. If a line runs different items, calculate ideal production minutes for each item before adding them together.

Calculate the losses on a common time basis

Downtime is already measured in minutes. Convert quality losses to equivalent ideal-production minutes, which lets all categories reconcile to one denominator. These equivalent minutes describe lost output capacity; they are not extra clock time spent inspecting rejected units.

Run time = Planned production time − Equipment failure − Setup and adjustments

Ideal time for total output = Total units × Ideal cycle time

Reduced-speed loss = Run time − Ideal time for total output − Minor-stop minutes

Quality-loss minutes = Rejected units × Ideal cycle time

Line A has 420 − 40 − 20 = 360 run minutes. Its recorded output represents 600 × 0.5 = 300 ideal minutes. The performance gap is therefore 360 − 300 = 60 minutes, comprising 25 minor-stop minutes and 35 reduced-speed minutes.

Line B has 420 − 15 − 30 = 375 run minutes. Its output represents 650 × 0.5 = 325 ideal minutes, leaving 50 performance-loss minutes: 20 minor-stop minutes and 30 reduced-speed minutes.

Loss, in equivalent production minutes Line A Line B
Equipment failure 40 15
Setup and adjustments 20 30
Minor stops 25 20
Reduced speed 35 30
Process defects 10 × 0.5 = 5 20 × 0.5 = 10
Startup rejects 20 × 0.5 = 10 10 × 0.5 = 5
Total losses 135 110

The residual calculation identifies the size of reduced-speed loss; it does not establish the cause. Review the underlying shift notes before attributing the gap to tooling, materials or operator practice. A downtime dashboard can support a separate review of significant-stop reasons.

Prove that every minute is accounted for

Line A produces 600 − 20 − 10 = 570 good units, equivalent to 570 × 0.5 = 285 productive minutes. Line B produces 650 − 10 − 20 = 620 good units, equivalent to 310 productive minutes.

Reconciliation Line A Line B
Productive minutes 285 310
Loss minutes 135 110
Productive minutes + losses 420 420
Planned production minutes 420 420
Unexplained difference 0 0

OEE.com's calculation guide gives the equivalent identity: OEE equals good units multiplied by ideal cycle time, divided by planned production time. Here that is 285 / 420 = 67.9% for A and 310 / 420 = 73.8% for B, rounded to one decimal place.

Across both lines, productive minutes are 285 + 310 = 595 and planned minutes are 420 + 420 = 840. Combined OEE is 595 / 840 = 70.8%. Use summed productive and planned minutes for larger groups, especially when shift lengths differ.

Turn the comparison into an assigned action

Line A's largest individual loss is equipment failure. Maintenance should review the recorded failures with production, select a documented cause and check the same category after the corrective work. Line B's setup and reduced-speed losses are tied, so the setup lead and process engineer should inspect those records before choosing a project.

Plant management owns the common definitions. Production owns stop coding, quality owns reject classification, and maintenance owns repair evidence. Finance can connect an approved improvement to manufacturing cost per unit, but equivalent production minutes are not automatically cash savings. Recovered capacity only has financial value under stated labor, demand and cost assumptions.

Where the analysis goes wrong

  • Counting short stops twice. Minor stops stay inside run time here; subtracting them before calculating performance and again afterward duplicates the loss.
  • Using an achievable average as the ideal rate. A slow reference hides speed loss. Document the ideal rate and review implausible results before comparing lines.
  • Inventing a missing split. Without recorded minor stops, the export supports combined performance loss, not separate minor-stop and reduced-speed findings.
  • Treating recovered rejects as first-pass good units. Rework recovery belongs in a separate record and must not erase the original reject.
  • Changing the scheduled-time boundary. Removing changeovers from one line's denominator makes its comparison with another line unreliable.

Compare your recorded losses in Covirage

Bring a production export with line, shift, planned minutes, recorded stops, output and reject counts. Covirage maps the columns, and its tools compute and check the loss comparisons; the external AI model explains the results with every figure traced to its rows. Create a free Covirage account and bring a sample of your own export.

See Covirage for industrial manufacturers for the business context.

Questions people ask

How do the six big losses relate to OEE?

Equipment failure and setup reduce availability. Minor stops and reduced speed reduce performance. Process defects and startup rejects reduce quality. Overall equipment effectiveness combines those three factors, while the six categories show which recorded losses sit behind the combined result.

Are planned changeovers excluded from production losses?

A changeover inside time scheduled for production is an availability loss in this calculation. Time when production was never scheduled sits outside the denominator. Document that boundary before comparing lines so that moving a changeover between categories cannot create an apparent improvement.

Can rejected units that are later reworked count as good output?

For a first-pass quality measure, units needing rework are rejected on their original pass. Later recovery does not erase the original quality loss. Keep rework movements separate so the same physical unit is not counted again as new production.

Can I analyze the six losses from production spreadsheets?

Yes, when the records contain planned time, significant stops, output and rejects, plus an agreed ideal cycle time. Separating minor stops from reduced speed also needs a recorded minor-stop total. Without it, report a combined performance loss rather than inventing the split.